Selecting Data For Sustainable Procurement In Construction
It is estimated that around 40-50% of natural resources are transformed into construction material, and that as much as 30% of all building materials delivered to a construction site end up in waste. To minimise this, it is important to ensure that the procurement process allows for careful and detailed planning of resource use during the project. In order to promote this, and encourage the use of sustainable materials, the following data should be captured during the project:
‣Total material use
The estimated material use during a project should be recorded. This data will include the type, quantity, and quality of the materials. Although the sustainability impact of material use will depend on the type and quality of the materials, capturing the quantity is essential, as projects with lower material use usually have a lower environmental impact. However, it is also important to take into account what % of this material is, as described below, reused or more sustainable.
‣Reutilisation of available materials
The quantity of materials available on-site that are reused during the project should be recorded. This is particularly relevant in refurbishment projects, where a pre-procurement evaluation of the quantity and type of available materials should be conducted. Generally, the more materials are reused, the lower the environmental impact of the project will be.
‣Use of sustainable materials
The quantity of more sustainable material use should be captured. Sustainable materials can include, for example, materials that comply with the standards of any existing accreditations (i.e. if they are Type 1 accredited ecolabelled materials). A higher use of these materials will usually lower the environmental impact of the project.
In a tender process, you can establish the use of materials with certain sustainability standards essential criteria.
Another option is to include these variables as part of award criteria, granting the highest score to those projects which, measured in kilograms (or tonnes) use the least amount of materials, reuse the highest amount of available materials, or use the highest amount of sustainable materials.
Vehicle and transport use
It is estimated that construction projects account for the largest share of both global final energy use (36%) and energy-related CO2 emissions (39%). Although not all of these emissions derive from vehicle use, it is also important to monitor and capture the following:
‣Vehicle use
The total vehicle use can be captured during the project. This data will normally include the number of vehicles used during the project, and the hours of use for each vehicle. Less hours of vehicle use will normally result in a lower environmental impact. However, this will also depend, as explained below, on the vehicles’ emission standards.
While vehicle load is a critical factor but also consider the whole supply chain, there’s not much value in seeking to reduce journeys for steel braces that were shipped from China if a European alternative exists.
‣Vehicle emission standards
The emission standards of the vehicles used during the project should be captured. The European Emission Standards can help as guidance. Despite being European, these standards have been used by UNEP to evaluate vehicle emissions in LAC and Africa, and West Africa has used these standards to develop their new vehicle emissions regulation.
The following emission standards are those established by Euro 3, the most widely used in LAC and Africa:
- Petrol: CO: 2.3G/km; THC:0.20g/km; NOx: 0.15 g/km/
- Diesel: CO: 0.66g/km; HC + NOx: 0.56g/km; NOx: 0.50g/km; PM: 0.05g/km.
‣Transport use
Transport use can be captured in kilometers, and can include, for example, the kilometres that workers have to do in order to get to the construction site. However, the transport use that can have the biggest environmental impact during a construction project is the one related to material delivery. This includes the number of material deliveries to the site, and the associated kilometres per mode of transport used.
Grouping shipments, sourcing local materials, and using more sustainable modes of transport will help to minimise the impact of transport use.
In a tender process, complying with Euro 3 emission standards can be set as a technical specification for all vehicles involved in the project. To encourage improvement, using vehicles that comply with Euro 4, or 5, can be set as award criteria.
Generated waste
Construction projects, especially those in the construction, refurbishment, and deconstruction stages, involve the generation of great quantities of waste. To minimise and monitor waste generation, the following data can be captured:
‣Waste generated
The quantity of waste generated during a construction project should be captured. This can be collected in terms of volume (m3) or weight (kilograms or tonnes). Information regarding waste should also include the type of waste generated (especially regarding hazardous waste).
Lowering the amount of waste generated during a project will also lower the environmental impact of the project. However, in terms of sustainability, it is also important to capture data that shows what % of the generated waste is diverted from landfill.
‣Waste diverted from landfill
Minimising waste generation will help to lower the environmental impact of the construction project. However, diverting the generated waste from landfill will also help towards minimising this impact. This data should also be captured, and it will include the volume (m3), or weight (kilograms and tonnes), of waste that is reused, or recycled.
In a tender process, one of the technical specifications set as essential criteria for bidders can be to divert a specific % of generated waste from landfill. For further specification, a target % of recycled, or reused, waste can also be set.
Supplier details
In order to monitor the economic and social impact of a construction project, data can be collected regarding:
‣SMEs, local, and women-led companies
Data should be recorded regarding the companies that are involved in the supply chain, especially the number of SMEs, local, and women-led companies.
‣Employee data
Data regarding the employees that will be involved during the project can be collected, including the employee data from the suppliers, and subcontractors. This data can include the number of employees contracted as part of the project, as well as the number of hours of work per employee.
In a tender process, the selection of local companies, SMEs, or women-owned companies can be favoured if there are certain targets that underpin this decision.
Resources
Including construction sustainability criteria in tender documents:
IHOBE provides examples of how to introduce sustainability criteria regarding construction materials on a tender document, as well as how data should be required of the bidders.
- EU Green Public Procurement Criteria for Road Design, Construction and Maintenance. 2016. European Commission
- EU GPP Criteria for Office Building Design, Construction and Management. 2016. European Commission